A quiet semiconductor test floor at night, one test handler open with a small brush beside the test socket, an impasto painting for a field story on finding recurring problems in control chart notes
🕓  

9

  MIN READ

Read the Notes, Not Only the Points


🎯 Quick Answer

What: A note on a control chart is a few words written next to a point when the chart shows a signal. It says what the person on shift found and what they did. Over time, the notes become a list of every cause the process has had.

Why it matters: A reaction plan deals with one signal at a time. It cannot show that the same cause keeps happening, especially when different shifts find it months apart. The notes can show it, but only if someone reads them together.

How to apply: Once a month, collect every note on the chart. Group the notes by cause, count each cause, and list the biggest count first. For any cause that shows up twice, name one person to find out why it keeps happening.

The payoff: Recurring problems are found from notes the team already writes. The team fixes the reason, and the same signal stops showing up.


A semiconductor assembly and test plant tested every finished unit before it shipped. For each lot, it plotted the yield on a control chart. Yield is the percent of units that pass the test. The chart had a reaction plan, and its last step was short: write what you found next to the point.

Two of those notes, written two months apart, helped the plant find and fix a recurring problem.

The first note

One evening, a point went below the lower control limit. Yield on one tester had dropped.

The operator followed the reaction plan. The first check was the test program version, and it was current. The second check was the contactor. That is the part of the tester that touches the leads, the small metal legs on each unit. Its pins were dirty.

The operator cleaned the pins and tested the failed units again. Most of them passed. The next point was back near the center line.

Then the operator wrote next to the point on the chart: "Contactor dirty. Cleaned it."

It took a few seconds.

The second note

Two months later, the same signal showed up on the same tester, on a different shift. The operator on that shift read the earlier notes and checked the contactor. The pins were dirty again. The operator cleaned them, and yield went back up.

The new note said the same thing as the first one: "Contactor dirty. Cleaned it."

Two notes, one question

The test engineer was the process owner for the yield chart. The engineer saw the two notes and asked a question: why does the contactor keep getting dirty?

The reaction plan had worked both times. Each operator found the cause and got yield back up. But the contactor got dirty again later. The checks could find a dirty contactor. They could not stop it from getting dirty. For that, the engineer needed to know why it happened.

Why the contactor kept getting dirty

Each time a unit is tested, its leads press against the contactor pins. The leads are plated with tin. With every test, a little tin stays on the pins. Over many thousands of tests, the tin builds up. Then the pins stop making good contact, and good units start to fail.

The written steps for the tester said to clean the contactor. They did not say when. So the pins were cleaned only after yield dropped. By then, some good units had already failed and had to be tested again.

What the team changed

  • The written steps for the tester now set a cleaning interval, based on the number of units tested.

  • The handler is the machine that moves each unit into the tester. It now counts the units and shows when cleaning is due.

  • The test engineer showed each shift the new step.

In the months after, no note on the chart said "Contactor dirty." Once the cause was fixed, the engineer moved the contactor check lower in the reaction plan.

How the notes showed a recurring problem

Until then, nobody had read all the notes on the chart together. Each operator read the latest few when a signal showed. That is how the second operator found the first note. A note from further back could easily have been missed.

So the engineer started a new habit: read every note on the chart once a month. The first time, the engineer went back six months. There were five notes:

  • Month 1: "Contactor dirty. Cleaned it."

  • Month 2: "Old program version. Loaded the current one."

  • Month 2: "Cause not found. Called the test engineer."

  • Month 3: "Contactor dirty. Cleaned it."

  • Month 5: "Handler jam. Cleared it."

Grouped by cause and counted, with the biggest count first:

  • Contactor dirty: 2

  • Old program version: 1

  • Handler jam: 1

  • Cause not found: 1

This is a simple Pareto chart. With five notes, the repeat is easy to see by eye. With fifty notes over two years, written by a dozen operators, it is not. A count makes recurring problems easy to see at any size.

The monthly note review

The engineer now does this on the first workday of each month. It takes a few minutes for each chart.

  • Collect every note from the month. If there were only one or two signals, look back three months.

  • Group the notes by cause. Use the same words for the same cause, so "contactor dirty" and "contactor pins dirty" count together.

  • Count each cause, and list the biggest count first.

  • For any cause that shows up twice, name one person to find out why it keeps happening. Set a date for the answer.

  • Count the notes that say "cause not found." If there are several, the reaction plan may be missing a check. Ask the operators what they looked at.

  • Update the reaction plan. Put the causes that come up most near the top of the checks. When a cause has been fixed, move it down.

Twice is the trigger on purpose. Two notes do not prove a pattern. But asking why takes little time, and waiting for a third or fourth signal means more units to test again.

What makes a useful note

A note only helps if someone writes it and someone else can read it. These four habits help.

  • Write what you found, not what the chart showed. The chart already shows that yield dropped. "Contactor dirty" tells the next person where to look.

  • Write what you did. For example, "Cleaned it" or "Loaded the current one".

  • Keep it to a few words. A note that takes seconds to write gets written on a busy shift.

  • Write "cause not found" when nothing was found. That note is useful too. Several of them in one month mean the checks need work.

Where this fits in DMAIC

Reading the notes is part of the Control phase of DMAIC, the five-phase method used in Lean Six Sigma. The control plan names the metric and the process owner. The control chart shows when the process changes. The reaction plan says what to check first. The notes record what each signal turned out to be.

When the count shows a cause that repeats, the team uses root cause analysis to find out why. The Five Whys and a fishbone diagram are the usual tools. On the test floor, a look at the pins and at the written steps was enough.

I write one of these every week, based on what actually happens on projects rather than what the textbook says should happen. You can join the newsletter here.


FAQ

What should you write on a control chart when there is a signal?

Write what you found and what you did, in a few words. For example: "Contactor dirty. Cleaned it." If you found nothing, write "Cause not found" and who you called. Write it next to the point, on the chart or in the chart's log, so the next person sees it with the data.

How often should you review the notes on a control chart?

Once a month suits most processes. If a chart shows many signals, review it every week. If it shows very few, look back over three months so there are enough notes to count.

What counts as a recurring problem?

For this review, any cause that shows up twice in the notes. Two times does not prove a pattern, but it is enough reason to ask why. Asking is quick. Waiting for the cause to show up a third time costs more product and more time.

Is a reaction plan enough to deal with a recurring problem?

No. A reaction plan deals with one signal. It finds the cause and gets the process back to normal. It does not ask why the cause happened. When the same cause shows up again, someone needs to find the reason and fix it. That is often a short root cause analysis, such as the Five Whys.

Do you need software to track control chart notes?

No. A paper chart with pencil notes works. Once a month, copy the notes onto one sheet, group them and count them. A spreadsheet helps once there are many notes, but you do not need one to start.

Write what you found next to the point. Read the notes once a month. When a cause shows up twice, find out why it keeps happening.


More Insights

Get the FREE special report with the newsletter

The Dirty Dozen of Process Improvement

Resistance almost never looks like resistance. It looks like agreement in the room, followed by nothing happening. This 22-page report covers the twelve struggles that quietly end improvement work, the tell that gives each one away early, and one move to try on each. It arrives as soon as you subscribe.

By subscribing you are agreeing to receive Field Notes from me by email, roughly one short piece a week. The report comes first. Unsubscribe in one click, any time.

Form Submitted. Please check your email to confirm your sign-up. Thank you.

Oops! Some Error Occurred. Please try again.